The current Moraga Road Underground Utility Conversion Project (Corliss Drive to Devin Drive) is in the last stages for the construction for the new underground facilities. All conversions from the existing overhead power source to the new underground system are complete, and PG&E recently removed their overhead lines from the wood poles along Moraga Road. Now both AT&T and Comcast need to perform similar work to allow the removal of all overhead lines and wood poles along the north side of Moraga Road. The utility work is expected to continue into May with occasional lane closures on Moraga Road.